> September 19, 2005
 > November 1, 2005
 > March 6, 2006
 > June 8, 2006
 > June 21, 2006
 > September 5, 2006
 > September 7, 2006
 > September 7, 2006
 > October 9, 2006
 > October 16, 2006
 > October 19, 2006
 > October 25, 2006
 > October 30, 2006
 > November 9, 2006
 > November 9, 2006
 > November 29, 2006
 > December 13, 2006
 > December 18, 2006
 > December 22, 2006
 > January 15, 2007
 > January 19, 2007
 > January 31, 2007
 > February 1, 2007
 > February 14, 2007
 > February 16, 2007
 > February 22, 2007
 > March 1, 2007
 > March 2, 2007
 > March 9, 2007
 > March 15, 2007
 > March 24, 2007
 > March 30, 2007
 > April 4, 2007
 > April 11, 2007
 > April 18, 2007
 > April 24, 2007
 > May 2, 2007
 > June 1, 2007
 > June 28, 2007
 > August 30, 2007
 > September 3, 2007
 > September 11, 2007
 > September 28, 2007
 > October 1, 2007
 > October 24, 2007
 > November 28, 2007
 > January 23, 2008
 > January 24, 2008
 > January 25, 2008
 > January 29, 2008
 > February 6, 2008
 > February 15, 2008
 > March 3, 2008
 > March 11, 2008
 > March 18, 2008
 > March 31, 2008
 > April 1, 2008
 > April 4, 2008
 > June 30, 2008
 > July 3, 2008

 

Expansion Continuing in Southern Africa

  1. Construction progressing well at Newcastle, KwaZulu Natal, South Africa's first gas-fired IPP;
  2. IPSA looking to increase size of Coega Project to 1,000 MW in initial open cycle phase;
  3. Elitheni coal reserves receive satisfactory preliminary geological report; and
  4. IPSA to work on emergency power, isolated generation and small CHP projects in the Region.

IPSA Group PLC ("IPSA" or "the Company"), the independent power plant developer in southern Africa , today announces a number of important developments for the Company:


  • The Company's initial power plant in Newcastle , KwaZulu Natal South Africa - the first gas -fired independent power project ("IPP") in the country - is now approximately 70 per cent. complete and is expected to produce first revenues in the fourth quarter of 2006;
  • IPSA has been asked by the Department of Minerals and Energy ("the DME") to consider increasing from 800 MW to 1,600 MW its combined cycle power generation project in the Coega Industrial Development Zone ("IDZ") with the first phase providing 1,000 MW through two 500 MW blocks for fast track development initially in open cycle using liquid fuel. The first capacity is now targeted for commissioning in early 2008;
  • The Company's 400 MW Elitheni mine mouth coal-fired project is advancing into the environmental impact assessment phase following satisfactory preliminary coal reserve reports; and
  • IPSA is now actively pursuing other emergency power, isolated generation and small combined heat and power (CHP) projects in the region based on third party funding


Peter Earl, CEO of IPSA, comments "We are very pleased to be on track at Newcastle both with regard to timetable and the revised budget. As anticipated at the time of our Admission to Aim, we are now growing our portfolio of projects on the back of our presence on the ground in the region. We are particularly excited by the positive reaction we have received from the DME to our initiatives to add capacity on the Coega site, and we strongly believe that LNG has a future in South Africa for power generation. We now plan to progress the public participation phase of our environmental impact study with all speed.

Lack of power generation reserve capacity in South Africa and neighbouring countries has continued to cause economic damage throughout 2006 and has led to electricity black-outs and load-shedding. IPSA is now becoming a significant developer in the region and has been invited by large corporations and governments alike to provide fast power generation solutions to alleviate the growing problem of power shortages throughout southern Africa . We continue to expect attractive returns for our shareholders."


(1) Power project at Newcastle

The Board of IPSA announces that the Karbochem power project at Newcastle , KwaZulu Natal is running to schedule. All of the heavy lift items (boilers, GT frames and the steam turbine) are now in position and ready for installation and the control building is substantially complete. The Directors estimate that the project is approximately 70 per cent. complete and envisage that the Newcastle plant will be generating first revenues in the fourth quarter of 2006.

As previously reported, IPSA has put in place bridge facilities with Standard Bank plc, London, in the amount of US $4 million to take account of any timing differences on the anticipated receipt of a grant from the DME towards the construction of the project under South Africa's programme to encourage small combined heat and power projects for which the IPSA Newcastle project qualifies.

The Company has initiated discussions with commercial banks in South Africa to provide Rand denominated funding for the Newcastle project in order to release equity for future developments. The project to date has been funded entirely from equity and it is envisaged that at completion the project will have the ability to release further cash for re-investment in other IPSA projects through debt drawn-down upon commercial operation.

In spite of substantial increases in some of the raw materials over recent months, project costs continue to be within the revised budget.


(2) Coega, Port Elizabeth

Earlier this year IPSA signed a memorandum of understanding for the lease of a 20 hectare site at Coega Development Corporation's Industrial Development Zone at Port Elizabeth , South Africa with the intention of developing a fast track combined cycle gas turbine ("CCGT") project of 800 MW.  This project was planned to operate initially in open cycle at 500 MW using liquid fuels. It was anticipated that the project would convert to being gas fired upon construction of a proposed third party developed and owned LNG receiving terminal at the IDZ.

The IDZ is considered an important element in South Africa 's policy of adding value to locally mined metals and minerals. A number of energy intensive metal-processing and smelting companies are considering moving onto the IDZ site subject to the availability of reliable, sustainable, regional generation of electric power.

Since signing its original agreements with the IDZ, IPSA directors have held a number of meetings with the DME during which IPSA was invited to consider doubling the size of its proposed Coega project in order to meet growing demand for electricity in the Eastern and Western Cape regions. As a result of these discussions, IPSA has now delivered formal offers to the DME and to Eskom for 1,000 MW of open cycle capacity available from early 2008 at prices which Eskom has described as "attractive". IPSA is now holding in reserve 1,000 MW of gas turbines while it negotiates an appropriate power purchase agreement ("PPA") with either Eskom or the DME itself under the The Electricity Regulations Act which came into force on 1 August, 2006 and which gives the Government of South Africa the power to sign PPAs outside the framework of a lengthy, formal public tender process providing that there is transparency and providing it can be demonstrated that the contracted power is the lowest cost solution available for South Africa.

IPSA believes that it can meet both of these requirements. Under the revised Coega project concept IPSA proposes to develop two separate 500 MW blocks. The total cost of each of these first phase 500 MW blocks is estimated by IPSA to be some US $150 million.  The balance of conversion to CCGT would cost a further US $120 to US $150 million for each unit.  IPSA is in discussions with a number of South African financial institutions regarding raising project finance for the two initial 500 MW units of the Coega project through the formation of a new IPSA equipment finance subsidiary called KitCo. IPSA has also taken steps to procure LNG for the combined cycle phase at Coega.


(3) Elitheni, East London

Earlier this year IPSA signed preliminary agreements which gave it an exclusive right to develop up to 400 MW of mine-mouth clean coal power capacity at the Elitheni coal deposit in East London .

The Board has been advised that initial reserve reports have confirmed that there are indeed commercially exploitable reserves of coal at Elitheni of a quality and quantity suitable for power generation activities. The coal mining company is submitting a formal application to the DME for a mining licence at Elitheni and is finalising its mining plan, which anticipates production to commence within six months. It is understood that further test drilling is likely to confirm that there is sufficient resources to justify a large scale mine mouth plant. IPSA and the Elitheni mining company are also exploring the possibility of using coal from the reserves for small CHP projects in both the Eastern and Western Cape to serve industrial users of power and steam who have found themselves subject to power restrictions as a result of lack of capacity or following the Cape Town power cuts of 2006.

 

(4) Other Projects

IPSA is now actively pursuing other emergency power, isolated generation and small combined heat and power projects in the region based on third party funding. IPSA intends to act as lead developer for small IPP power plants that are fully funded by third parties but where IPSA can earn both management fees and carried interests or favourable acquisition rights using its experience as an international developer in regional markets where privately owned power plants are a new concept and where IPSA's ability to source generation equipment quickly or on highly competitive terms gives IPSA's development team an advantage.

Accordingly IPSA is currently considering emergency power, isolated generation or small combined heat and power projects serving large corporations or national governments in Botswana , Kenya , Madagascar , South Africa and Tanzania in addition to its existing combined heat and power projects in Swaziland and in the Prospecton Basin of Durban.



For further information please contact:

Peter Earl, Chief Executive, IPSA Group PLC: 020 7793 7676
Elizabeth Shaw, Chief Operating Officer, Group IPSA PLC: 020 7793 7676
Stephen Hargrave, Chairman, IPSA Group PLC: 020 7793 7676
Mark Froggatt, Noble & Company Limited: 020 7763 2200
Allan Piper, First City Financial Public Relations: 020 7436 7486
  07736 064 982